G & W Electric
ISO 9001: 2000 and 14001 Certified
Overview
Padmount Switchgear
Vault Switchgear
Overhead Switchgear
Reclosers
Automation Products
Current Limiting System Protection
Cable Accessories
Junction Bars
   
     

Application Guide
Puffer Vacuum Interrupters

TABLE OF CONTENTS:

Description
Standard Padmount Switchgear Application
Unique PVI Advantages
Special Padmount Applications
Vault PVI Switchgear Applications
Summary

OVERVIEW
This guide provides a brief description of G&W's Puffer Vacuum Interrupter (PVI) SF6 switch and it possible applications on distribution systems. The guide looks at the use of the PVI as a replacement for air or oil insulated padmount gear and identifies unique application benefits.

DESCRIPTION
The Puffer Vacuum Interrupter (PVI) provides great flexibility in meeting the requirements of underground distribution systems rated 5kV through 38kV. It is designed to eliminate many of the shortcomings of conventional air or oil insulated switchgear that has been used by both industry and utilities for many decades. While many of these problems associated with other gear have become accepted as obstacles that must be worked around, the PVI supplies an attractive alternative that tackles these limitations head-on.

Vacuum Interrupter Fault Protection
The fault interrupting mechanism of the PVI is unique. Unlike typical fusing, the PVI makes use of Vacuum Interrupters that combine vacuum bottles and electronic controls to clear faults with a wide variety of time-current characteristic curves to protect the downstream distribution system. The resettable Vacuum Interrupter means that fuses are no longer required when the PVI is used in place of most padmount equipment. In addition, the electronic controls can be set for either single or three phase trip, thereby preventing single phasing conditions common to fusing constraints. Finally, the Vacuum Interrupter is rated up to 600 amps continuous current, so fault protection above 200 amps is much more readily available using the PVI. See Figure 1 for basic operation sequence.

Figure 1: PVI operation sequence

In addition to providing fault protection, the vacuum bottle can be operated manually to act as a load break switch. Many utilities require a separate switch on the tap (fuse) side in order to change out fuses. With the PVI, this requirement is no longer necessary. It is important to note that even though the vacuum bottles are surrounded by SF6, any high energy fault or load break interruption is done within the vacuum bottle.

Puffer Load break Interruption
The 600 amp load break switch technology used for source switching offers some unique features above standard load break switches. The PVI uses Linear Puffer load break switches for the source side of the switchgear. The Linear Puffer design concentrates a burst of SF6 gas in the arc zone of the switch that minimizes contact wear and maximizes the life of the switch without maintenance. See Figure 2. In addition, the switch can be rated up to a 40kA momentary or close-into- fault condition, far above most switch ratings. A Rotary Puffer design is also available offering ratings through 27kV, 20kA asymmetric momentary. The Puffer switch is an ideal choice for either automatic transfer control or possible distribution automation schemes.

Figure 2: Linear Puffer Load break Principle.

One common requirement of load break switches is that the opening of the switch provide a visible disconnect for operating crews to identify when a switch is isolated from line voltages. The Linear Puffer switch in the PVI provides this visible disconnect through viewing windows on the unit by the operating handle. All three phases can be seen through the window to insure the switch is open prior to working on the switch or downstream devices.

The PVI unit is built inside of a fully sealed, dead-front tank that is filled with SF6 (Sulfur Hexafluoride) gas. The SF6 gas provides the dielectric strength to the electrical components and supplies two primary advantages above other dielectric compounds. First, like oil, SF6 gas has a dielectric strength, roughly 2 to 3 times higher than air, which allows the tank to be compact and built with a minimum of insulating barriers. Fortunately, SF6 gas is not combustible like oil so has no danger of the dielectric becoming flammable and causing safety problems. Second, unlike air, the SF6 gas does actually have arc- extinguishing properties that minimize maintenance and maximize equipment life. The PVI equipment is anticipated to have a 30+ year lifespan with virtually no maintenance required.

STANDARD PADMOUNT SWITCHGEAR APPLICATIONS
The PVI can be used as a substitute for other types of padmount gear in almost all applications. The wide variety of available standard industry configurations allows the PVI to be a direct replacement for any deadfront switchgear. The unit may be used for a livefront replacement by changing the cable terminations to elbows. Note however that the PVI enclosure footprint will be larger than most livefront gear, so pad dimensions may need to be examined prior to a change-out.

The single most important decision to make in selecting the correct PVI is the proper configuration for the specific location. The available configurations are shown in Figure 3. Determination of the configuration is based on the type of distribution system that is being installed.

Figure 3: PVI one-line configurations

Distribution Systems Design Methods
Distribution systems are generally broken down into either radial or loop systems for general discussion. In many cases, the two types of systems will both be used within a company and often within the same distribution feed.

Nevertheless, the difference between a loop and radial feed is key in determining the proper configuration required for the PVI. A loop system is almost always installed with two load break switches involved in the design. With the two load break switches, the loop can be opened from either direction, which allows great flexibility in selecting the open point of the loop and in isolating the switch when work is required. Therefore, a PVI-6, 9, 10, 11, 13, or 14 is most commonly used in loop designs.

In the case of radial feeds, a single load break switch is required to provide the visible disconnect associated with working on the switch after determining that the switch is isolated from line voltage. Therefore, common configurations of the PVI used for radial feeds are the PVI-3, 5, 7, and 12. Note that a radial feed that will be converted into a loop feed in the future should normally be installed as a loop-style switch (two or more load break switches) as opposed to adding a second switch in the future. The engineering trade-off in determining whether to use a loop or radial system is primarily cost versus reliability. The radial feed is less costly but also provides less reliability, since the source can only provide power along a single path. If the radial path has a faulted conductor or outage, the load can not be served until the problem is repaired. This repair may take hours or days depending on severity and accessibility of the location.

The loop design has a higher cost associated with the installation, but also offers a higher degree of reliability. In most cases, the loss of power through one source can be compensated for by feeding all loads through the second source. Also, a faulted conductor can be compensated for in a short time period by switching the load break switches so that the faulted cable is isolated from the sources and loads. Under most circumstances, all customer loads can be re-energized and served by isolating the faulted line with the sectionalizing switches and repairing the line after customers are back in service.

Figure 4A shows the situation that occurs when a radial feed experiences a fault, while Figure 4B shows how a loop system can be re-configured to isolate the faulted line and bring customers back into service quickly. In general, utility engineers are moving towards loop systems for at least the major lines to maintain higher reliability levels.

Figure 4A: The radial feed design is a good method of supplying power to a load where reliability is not critical. However, Figure 4.A.2 shows that a fault in the radial line will remove the load from service until the fault is repaired.

Figure 4B: Looped systems offer far more versatility in re-establishing service to customers under fault conditions. In order to restore power to all loads after the fault occurred in Figure 4.B.2, only one switch needs to be opened by the crews prior to restoring power. Other fault locations would require closing the normally open switch and opening two other load break switches to again restore power to all loads. The fault can now be repaired at a later time by fault locating specialists since no customers are impacted.

Basic Radial System Designs
Common placement of switchgear and possible configurations are shown in the following one-line diagrams. Figure 5A shows a simple radial feed system and how the PVI gear may be utilized. In this simple system, the three phase distribution lines feed a single load through a PVI-5 unit. Figure 5B shows a more complex radial system where a combination of PVI-5, PVI-11 and PVI-7 units feed loads from a single radial feed.

Figure 5: Examples of typical radial feed line designs.

The PVI-11 allows the single incoming source to be split into a VI tap near the switch, plus provide sectionalizing capability for two other cabinets on the distribution feed. The PVI-5 unit provides a simple Puffer load break switch in series with a VI protected tap for a single load. The PVI-7 design adds a second tap for multiple load protection.

Note that the equipment can be used to protect either single phase loads (denoted "1 phase") or 3- phase loads (denoted "3-phase") by selecting the proper setting on the electronic control panel. Unlike normal fusing, the VI"s with the electronic controls set in "3-Phase" mode will trip all three phases at once for protecting 3-phase loads. This capability provides single phasing protection which assists in protecting both 3-phase motors and 3- phase transformers against problems caused by single phasing.

Basic Loop Design Systems
Figure 6A shows a basic loop design that consists of two sources feeding through two PVI-9 units into a loop with three sectionalizing cabinets. Loads are fed from the VI's for overcurrent protection. Figure 6B shows a similar system that is fed from a single utility source. The advantage of the loop in this case is that the loads can be fed from two points along the source in case a portion of the source line becomes faulted.

Figure 6: Dual sources provide higher reliability (6A), but are normally more costly. A single source (6B), feeding a loop at two different points decreases the effect of losing a load due to cable failure.

Hybrid System Designs
In many cases, the utility will design a hybrid system that consists of both loop and radial feeds. The major source feeds (backbone) will be configured as a loop, while the tap points off of the loop may be either radial or loops. Figure 7 shows an example of a hybrid system that contains a backbone loop with a secondary loop in one area and radial feeds for the rest of the system. Note that the secondary loop is actually protected by VI's rated at 600A continuous current, which is difficult to accomplish with standard padmount switchgear. This capability offers the advantage of not only having sectionalizing capability at the two source switches, but also limiting outages due to possible faults in the 600 amp cable feeding the secondary loop. This is accomplished by limiting the outage to the first VI instead of taking out a much larger service as typically is required by using load break switches on the backbone of the system.

Figure 7: A hybrid system where the major feed (backbone) is a loop system and most other feeds are radial. Note in the dashed section that there is a secondary loop that feeds (SEC. 7.A) 2 other switches. This second loop is protected by VI's that are set to 600A protective curves which is normally difficult to accomplish with standard padmount switchgear.

Naturally, this capability is also available for radial loads being fed from 600 amp rated VI taps as well. In this case, a fault on the single line feeding the radial load would clear at the VI instead of going back to the breaker. This capability will improve reliability by limiting outages to smaller sections of the system, which is a major advantage in many cases.

Figure 8 contains a more complex system that has a loop for a backbone and combination of loops and radial feeds to handle customer loads based on reliability requirements. In Section 8A, the secondary loop is fed from the Puffer load break switch as is more typical in standard padmount installations.

Figure 8: Hybrid system with a backbone loop fed by two sources. A secondary loop (SEC. 8A) is also fed from the main loop as shown in the dotted section at the right of the diagram. All other circuits are radial feeds using a variety of PVI configurations.

Automatic Transfer Design Systems
A level of reliability that exceeds that of the loop is to have two sources feeding a load that will automatically transfer to an energized circuit when the primary feed is interrupted. The advantage to the customer is that the transfer between sources can happen in seconds or even cycles instead of waiting minutes or hours for a crew to make their way to the site and manually throw over the switches. A common one-line diagram is shown in Figure 9. The PVI-6 or 9 configuration is typically supplied for this application, although any PVI unit that has 2 or more Puffer switches can be used.

Figure 9: The addition of automatic transfer control (ATC) package dramatically reduces outage time for a customer that requires continuous power by automatically switching to the second source if an outage occurs on the primary source.

A number of options are available when ordering the Automatic Transfer Control (ATC) package. Decisions need to be made on open versus closed transition, time delay settings for both initial and return switching, and if the switch may be monitored via SCADA in the future. Contact your G&W sales representative to resolve these issues.

UNIQUE PVI ADVANTAGES
In addition to the PVI being used as a substitute for standard padmount gear, the design offers special features that can alleviate problems inherent to older designs incorporating the more traditional switch and fuse concepts. Most of the advantages are in eliminating the fuse and replacing it with the electronically controlled vacuum bottle, but the Puffer load break switch offers advantages as well.

Three Phase Tripping
The electronic controls for the PVI fault protection system allow the user to select the proper settings as required for the specific location. These include setting the trip points (similar to setting the fuse size in standard gear) within a range of 12 available pre-selected points. As important, a switch for selecting single phase or three phase trip is available on the control panel. See Figure 10A for a layout of the standard Type 1 panel.

Figure 10A: PVI electronic control standard panel layout

Single phase trip may be used for all single phase loads which are typical in residential areas. This is equivalent to a fuse tripping and opening up the single phase that contains the fault on a three phase circuit. For this circumstance, only the customers fed from this phase of the circuit are out of service until the repair is complete.

However, many industrial and large commercial loads may be better served by selecting a three phase trip setting. Three phase trip will interrupt all three phases even if only a single phase has a fault, similar to a circuit breaker. Three phase trip is typically used to protect three phase transformers and motors that can be damaged by single phasing. In particular, even if the motors have three phase protection built into the motor starters, the three phase transformers that feed these loads are subject to ferro-resonance conditions that often damage equipment. The PVI provides a cost-effective way of providing protection to both motors and transformers in these conditions.

Standard Electronic Controls Capability
All PVI units are supplied with standard electronic controls for each Vacuum Interrupter. The standard controls are supplied with a Single Phase / Three Phase selector switch and a selector switch for each phase that allows the trip set point to be selected from one of twelve pre-selected settings as shown in Figure 10A.

Trip level ranges are 15 to 300 or 30 to 600 amp settings that correspond to the time current characteristic (TCC) curve selected during the order process. Each unit is programmed with multiple TCC curves, e.g. E-slow, E-standard, EF, K, NX, Oil Fuse Cutout, QA and selected overcurrent relay curves. A dip switch allows the user to choose the TCC curve to match individual coordination requirements. Vellums are available upon request to assist in coordination studies.

The electronic controls are powered through the current transformers that sense the current flowing through the load side of the vacuum bottles. A minimum current of approximately half of the minimum trip setting is required to keep the electronics energized and protecting the load. If this current level is not available prior to a fault, the TCC curve that is protecting the load may be slowed by a maximum of the greater of .5 cycles or 10% of the trip time.

Note that if a protection package is selected that exceeds 300 amps, or if anticipated load growth may push the load to over 300 amps continuous in the future, the PVI should be ordered with 600 amp bushings on the Vacuum Interrupter side of the equipment. The vacuum bottle and all associated buswork is rated to 600 amps, but the 200 amp bushings will de-rate these ways to 200 amps continuous unless the 600 amp bushings are selected. Many conditions can change over the anticipated 30+ year lifespan of a padmount unit, so the PVI will allow the change out of the electronics if required. If a new TCC curve set is needed, the controls can be easily changed in the field.

Optional Electronic Control Schemes
A number of options are available to extend the features to the PVI electronic control schemes if required. An enhanced electronic package, Type 2 Figure 10B (three phase only) is available and offers the following features:

Figure 10B: PVI electronic control
Phase Selector/Manual Trip optional package layout.

A Ground Fault control provides a three phase comparison of current values to determine when a ground fault is present on the load side of the Vacuum Interrupter. If a ground fault or an overcurrent condition is detected, the controls will trip all three phases of the Vacuum Interrupter. The Ground Fault control panel provides a maximum percent of phase imbalance selector switch and a timer to set the ground fault parameters.

The enhanced package also provides a selector switch for an Adjustable Phase Time Delay. This permits coordination of other protection devices which may be in series with the switch. A delay time from 0 to 0.15 seconds (up to 0.5 seconds for later models) is provided.

In addition, a Manual Trip Button is provided permitting electronic tripping of all three phases from the controller.

An External Contact control is included for connecting an external relay or sensing device to trip the electronic controls. The standard TCC curves are also available if desired for tripping on overcurrent conditions. An example of how the External Contact package may be useful is where a transformer sudden over-pressure relay can be tied into the Vacuum Interrupter controls to automatically trip the VI if an over-pressure condition occurs. Many external devices can be used as well based on the application. These situations would also call for the External Power capability, which allows an external power supply to feed the control package to make certain that the controls will operate independent of current flow.

For situations where the TCC coordination is very tight, the External Power is included to ensure that the controls will be continuously powered even if there is no load on the Vacuum Interrupter. This option does require an external 120V AC or 24V DC power supply, 1mA current maximum output.

Superior TCC Curve Matching
Since the electronic controls do not depend on a melting element to clear, they maintain a much more consistent Time-Current-Characteristic (TCC) curve. Most fuses are specified as meeting the TCC within a plus-or-minus 10% range. The electronic controls in the PVI are rated to plus-or-minus 3%, which can be helpful in situations where the coordination scheme is tight.

In addition, common fuse curve problems are eliminated by the electronic controls. “Sneakouts” are fairly common in fuses that are subjected to high levels of current relative to their ratings for short time periods, e.g. during motor start-up. Fuses subjected to these conditions often fail during near nor-mal operation and never at a convenient time. Fortunately, the VI unit eliminates sneakouts by tripping based on the actual current exceeding pre-defined TCC curves independent of prior overcurrent conditions.

Vacuum Interrupter Reset vs. Fuse Replacement
The Vacuum Interrupter is a resettable device that clears faults by opening up the vacuum bottle contacts to break the fault current. Testing proves that the bottle will last through a large number of fault break operations, dependent on the actual fault levels available. Under reasonable circumstances, the Vacuum Interrupter will last over 30+ years with-out need for maintenance.

Since the vacuum bottle clears faults and can be reset, the need for fuse replacement is eliminated. Fuse replacement may be costly, is never timely, often results in improper fuse sizing being installed at a site, and may be a safety issue for the crews that are called on to replace failed fuses by closing a new fuse into a possibly still faulted conductor. The Vacuum Interrupter eliminates these problems.

Frequently Switched Padmount Units
The Linear Puffer load break switch offers the strong advantage of having been tested to over 1200 operations at full 600 amp load without failing. As a result, the PVI should be considered for any location that requires frequent switching. Common applications include using the PVI for automatic transfer control schemes and distribution automation where the load break switch may be operated frequently through automation.


SPECIAL PADMOUNT APPLICATIONS
The PVI has a number of unique features that allow it to be used for situations that are not easy to accomplish with standard gear. These include using the front-accessible PVI switchgear in situations where either normal switchgear would require two separate padmount units or where space is tight and a standard front and back accessible unit is difficult to place. In addition, some special switchgear designs are available for specific problem areas, e.g. requirements for a bus tie switch in a single tank unit.

Front-Accessible PVI Designs
A fairly common situation that occurs during distribution system design in congested areas is a requirement for more than two taps feeding from a loop system. Because of the need for two load break source switches for a loop, the common solution is to use at least two padmount units to meet the requirements for three or more fused tap compartments. This design may end up looking something like that shown in Figure 11A.

Figure 11A is the normal method of meeting a requirement that calls for more taps than are available in a standard 4 bay padmount unit. Figure 11B shows the design using the front-accessible PVI. Since the PVI is expanded to six bays with four protective taps, there is no longer a need for two padmount units and the associated real estate, cabling, two pads and vaults and extra terminations otherwise required.

Figure 11: Comparing normal padmount requirements for multi-tap applications to the use of front-accessible PVI switchgear.

In addition, the front-accessible gear is wider than standard designs, but significantly more shallow so that overall space required is minimized. One other feature that is attractive in the front-accessible gear is that the equipment can be placed against a wall with no impact to operating access. In a situation where aesthetics are important or real estate is particularly valuable, the front-accessible PVI be-comes a very attractive option to either standard padmount gear due to smaller space requirements (only front access is required, so no side or back work access space is needed) or to placing the switchgear in sub-surface vaults. In comparing the front-accessible gear to placing all equipment in vaults or basements, the front-accessible gear is significantly less expensive.

All of the front-accessible PVI designs are shown in Figure 3. The more common standard numbering system is used for all units that have four or less bays, e.g. PVI-6F or PVI-9F (See Figure 12). Since industry standards are not available for more than four bays, G&W adopted a numbering system that first has the number of total bays, then supplies the number of load break switches in the unit. For example, the PVI-62F has a total of six bays, with two Puffer load break switches and four Vacuum Interrupter protective taps.

Figure 12: Drawing of a standard front-access PVI-9F.

Bus Tie Applications
Another situation that is difficult to handle with standard padmount gear is achieving a bus-tie scheme. In most cases, this is used in industrial applications that require two sources feeding two or more taps with a center switch that can be opened to prevent the sources from paralleling or preventing an overload condition on a single source unknowingly. This is frequently accomplished with the use of metal-enclosed switchgear.

An alternate to this bus-tie scheme can be accomplished with a PVI unit that incorporates a center switch. In the case of a simple bus-tie with two VI taps, the PVI can accomplish the same function in a single tank that is much less obtrusive. Multiple Vacuum Interrupters can be incorporated if required by using additional front- accessible PVI's as needed. Contact your G&W field sales representative for additional information.

Integral Ground Position Applications
For applications requiring system grounding at the switch, G&W PVI switches can be supplied with an integral third switching position permitting safe and easy grounding without having to disconnect elbow or other cable entrance connections. Switches can be designed for front access only, or with front/back access to cable compartments and operating apparatus. The puffer source operating mechanisms provide ground stops with padlocking provisions to help assure proper operation in the desired position.

G&W three position Triad Series switches are rated through 38kV, 25kA asymmetric momentary and incorporate a rotary puffer style contact system. Rotary puffer style contacts are also available for two position PVI applications where the maximum short circuit current is below 20kA asymmetric. Rotary puffer style switches permit a smaller switch construction and should be considered, were ratings permit, for confined space requirements.

VAULT PVI APPLICATIONS
The PVI gear is also designed for placement in vault or subsurface locations. The major change in construction versus the padmount design is that the PVI is designed for total submersion by using all watertight control housings and cables, plus the padmount enclosure is not supplied with the unit. Most customers prefer to use the front-access style design due to the tight space available in vaults. As a result, all of the designs shown in Figures 4-9 are also available in the front-access style, although front and back designs are available for vaults if required.

Use of the vault PVI (VPVI) switches is normally similar to the uses listed in the padmount sections. Again, loop versus radial decisions must be made prior to determining the proper configuration based on number of load break switches required. The other important decision is regarding the number of taps required to provide overcurrent protection. Since most of the vault installed units are supplied with front-accessible designs, going from one VI tap to four or five is normally a matter of increasing the width of the tank by an additional two feet per tap (approximate).

If the VPVI is going into a vault with a manhole opening, the opening size may be a concern. The smallest round manhole opening that will allow a VPVI unit to fit is 46 inches. Many vaults also provide the capability of removing the top for placement of large items which may lower this concern for many applications.

Refer to Figures 4 through 9 for a description of common design scenarios. Any of these designs can be used with the VPVI units to provide sound distribution systems that will meet most customer requirements. Contact your local G&W representative to discuss specific system requirements that may not be listed above.

SUMMARY
The PVI allows the distribution system designer to incorporate many advantages that have not been present with past switchgear products. In addition to the standard switchgear applications of switch and fuse capabilities, the PVI offers many features that add flexibility for both customer and designer requirements. Primary advantages are in the VI design and operation. The Vacuum Interrupters supply the capability of having a resettable fault interrupting device as opposed to a replaceable fuse. Also, the electronic controls supply either single or three phase trip capability by making field selectable adjustments. The VI also provides the ability to protect continuous loads above 200 amps (up to a maximum of 600 amps) by specifying 600 amp bushings and the proper electronic control TCC curves at time of order.

In addition to the advantages supplied by the VI, the Puffer load break switch supplies a far larger number of operations without maintenance required than other switch designs on the market. As a result, the Puffer switch is ideal for applications involving frequent switching, e.g. automatic transfer or automating the distribution system equipment.

Finally, in addition to padmount and vault switchgear, G&W offers an extensive range of overhead switchgear as well. Sectionalizing switches are available that use Puffer load break switches, and fault protection can also be supplied with overhead VI designs. In combination with automation control schemes, automatic fault sectionalizing can be set up to increase reliability on the overhead system by using G&W equipment.

In short, the PVI offers the next generation of distribution switchgear designs available today. After examining the information in this product guide, please contact your local G&W representative to discuss specific applications of the PVI switchgear for use on your system.

 

 
Site Map